SECRET
Page 307
2.
PHANTOM: MCDONNELL/FERRANTI CONTRACTUAL POSITION (Previous reference: OPD(67) 32nd Meeting, Item 1)
The Committee had before them a memorandum by the Minister of Technology (OPD (67)80) on the contractual position between McDonnell and
Ferranti for the navigation attack system for the Spey Phantom.
THE MINISTER OF TECHNOLOGY said that, following the decision in 1965
that a Ferranti navigation attack system should be fitted in Spey Phantom
aircraft that we were purchasing from the United States, it had been decided
that the responsibility for making the contract for the supply of this
equipment should be given to the United States aircraft firm, McDonnell,
instead of the contract being placed by ourselves direct with Ferranti.
This had been done because the navigation attack system had to be fitted in
with the airframe and equipment as a whole and it had seemed desirable that
McDonnell should be responsible for the complete task. Doubts which had
since proved to be justified, about the ability of Ferranti to develop and
produce the equipment on time, had led us to press for clauses providing
for liquidating damages against late deliveries of the equipment to be
included in the contract between McDonnell and Ferranti, and the Ministry
of Technology had been given to understand in late 1965 that this would be
done; it subsequently emerged however that McDonnell had dropped this
requirement during contractual negotiations. The Ministry were not aware
of this until after the event and could only have insisted on the inclusion
of such clauses had they themselves made the contract with Ferranti.
Although the belief that there would be such penalty clauses in the contract
had been a factor in the decision to fit the Ferranti system into the Spey
Phanton, since it had increased confidence in the equipment, he believed
that other considerations would have led us to choose the Ferranti system
even had the Ministry of Technology made the contractual position clearer.
In discussion the Committee were informed that delay in the delivery
of the Ferrenti navigation attack system was likely to be less than had
previously been expected. But the programme would still be delayed by
twelve months and this would mean that the first sixty or seventy Spey
Phantom aircraft would be delivered without an adequate navigation attack
system; although this was a serious delay, it would in part be masked by
--
Page 307
SECRET
Page 307
No comments yet.
Private notes are available after approval.